1. It is to establish the template of the luminous pavement. Before pouring the concrete, side molds should be set up, and the setting of the template should meet the design requirements, should be level and firm, and steel molds should be selected. The width of the pavement that exceeds 5 meters should be a segmented template, and the section width is generally 4-6 meters. The section should be combined with the position of the expansion joint. Different pavement materials and different color models of the floor should be divided. The manhole can be placed in advance so that it is flush with the ground. If the template is made of stone or other materials, pay attention to protection and place it contaminated.
2. Proportioning the cushion concrete. The concrete construction party must control the water-cement ratio and slump, which is the key to affecting the quality of the project, which can effectively improve the work efficiency and improve the quality of the project and reduce the occurrence of bleeding.
3. During construction, the concrete that is required to be mixed during the on-site construction of luminous pavement shall not have segregation, bleeding, inconsistent slump, and insufficient markings. Early strength, retardation or other chloride-containing admixtures shall not be used. At the same time, calcium chloride and its products should not be mixed, and air-entraining agents should not be used.